Critical Chain
Project Management
(CCPM) | | |
Turn In When Complete
Remove all incentives to date-driven behavior, causing people to turn in work as soon as it is complete,
rather than
'polishing the apple' or holding it for review because it is not due. You aid this a by not publishing
task 'due dates.' Assure
that contracts do not have incentives to continue to work on a task; e.g. avoid time-and-material contracts,
and substitute
payment on deliverables.
|