Critical Chain Project Management (CCPM)

bullet1 Exploit
bullet2 Roadrunner Performance

bullet3 Thumbs up   Turn In When Complete

Remove all incentives to date-driven behavior, causing people to turn in work as soon as it is complete, rather than 'polishing the apple' or holding it for review because it is not due. You aid this a by not publishing task 'due dates.' Assure that contracts do not have incentives to continue to work on a task; e.g. avoid time-and-material contracts, and substitute payment on deliverables.