Critical Chain Project Management (CCPM)

bullet1 Identify
bullet2 Project

bullet3 Critical Chain

The critical chain is the constraint of a single project. It is the longest path through the project, considering both the task logic and resource availability and demand. With unlimited resources, the critical chain is the same as the initial critical path. The critical chain does not change during project execution. (Critical path can change during CPM (Critical Path Method) project execution as tasks take more or less time than their deterministic estimate.)