Critical Chain
Project Management
(CCPM) | | |
Cost Buffer
The cost buffer accounts for variation in project task cost. You should estimate it using methods similar
to sizing the
Project time Buffer, but consider all tasks in the project as cost does sum for all tasks in the project.
The cost buffer
requires a variational element and a bias element.
|