Critical Chain
Project Management
(CCPM) |
|
|
Elevate
Elevate is the fourth of the five focusing steps of the Theory of Constraints (TOC). It means getting
more of the constraining
resource. Frequently many cycles of the first three steps are required before the constraint must be
elevated. Elevating a
resource (such as hiring more people or buying more machines) usually requires investment ($) and time,
while exploiting
and subordinating can happen immediately and usually cost little or nothing.
|